2009-UK-13027-E:
A14 Corridor traffic management scheme |
|
|
 |
|
This project is part of Priority Project 13 (United Kingdom/Ireland/Benelux road axis).
The proposal will improve traffic conditions along 3 heavily congested sections of the A14. This will be achieved by installation of:
- Incident detection and automatic signing, traffic detection system and queue protection using variable message signs on cantilever structures.
- Strategic diversionary message sign information at specific junctions
- Extensive close circuit television (CCTV) coverage for improved incident response
Through wider dissemination of the data collected, significant accident reduction and delays saving will be achieved by warning drivers of upcoming accidents and advising them of preferred diversionary routes.
The project will also contribute to the ongoing EU ITS initiatives including EASYWAY and the ITS Action Plan.
This project has been completed.
See our TEN-T project implementation successes section for more information.
|
Budget:
National budget:
€46,687,800
|
Total project cost covered by this Decision:
€58,357,800
|
Percentage of EU support:
Works: 20%
|
|
EU contribution:
€11,670,000
|
Download the Info Sheet about this project:
.pdf (408.9 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
United Kingdom
Implementation schedule:
Start date: May 2009
End date: May 2011
Beneficiary:
United Kingdom of Great Britain and Northern Ireland
Implementing body:
Highways Agency
Additional information:
European Commission, DG MOVE
|
|
|
|
|
|
 |
|
|
|
 |
(Mailing address) TEN-T Executive Agency European Commission W910 B-1049 Brussels |
 |
(Visiting address) Chaussée de Wavre 910 B-1040 Brussels Belgium |
 |
 |
 |
|
 |
|
 |
|