This Action concerns the prototyping, testing, certifying and serial retrofitment of 55 Siemens ES64U2 locomotives with ETCS Level 1 and Level 2, SRS 2.3.0d.
The retrofitted locomotives will circulate on a significant part of Corridors A, B and E, including the connecting networks in Germany, Austria, Hungary and Switzerland. The interoperability will be extensively tested both in laboratory and on-site during the prototype phase.
The Action includes the following activities:
- Prototyping, testing and certifying
- Interoperability test in independent EU certified laboratories
- Retrofitting
|
Budget:
Action promoter:
€6,840,000
|
Total project cost covered by this Decision:
€13,680,000
|
Percentage of EU support:
Works: 50%
|
|
EU contribution:
€6,840,000
|
Download the Info Sheet about this project:
.pdf (456.2 KB)
This project was also the subject of a press release issued by the Agency. |
 |
 |
| Click map to view enlarged version |
Member States involved:
The Netherlands
Implementation schedule:
Start date: April 2011
End date: December 2013
Beneficiary & Implementing body:
Mitsui Rail Capital Europe BV
Additional information:
Coordinator’s Report of the Priority Project
European Commission, DG MOVE
|