2009-NL-60123-P


Upgrade of ETCS system to 2.3.0d in the Betuwe Route


In The main objective of the Action is to upgrade the Betuwe Route trackside ETCS system to become compliant with the ETCS 2.3.0d specifications.

The upgrade includes replacement of the present software in two Radio Block Centres (RBC) by a 2.3.0d-compliant software version. It includes reprogramming a limited number of balises and the performance of tests and updating the documentation.

 

The Action includes two sub-activities:

 

1. Upgrade of trackside ETCS elements to comply with 2.3.0d specification

2. Implementation of the testing strategy

 


 

State of progress on 31 December 2011:

The Action has started in February 2011 and is ongoing.

 

Budget: 

 

State Budget:

 

€1,000,000

Total project cost covered by this Decision: 

 

€2,000,000

 

Percentage of EU support:  

 

Works: 50%

EU contribution: 

 

€1,000,000

 

Download the Info Sheet about this project:

 .pdf (285.9 KB)

Click map to view enlarged version


Member States involved:

The Netherlands

 

Implementation schedule:

Start date: January 2010

End date: December 2012

 

Beneficiary & Implementing body:

Prorail BV

 

Additional information:

 Coordinator’s Report of the Priority Project

 European Commission, DG MOVE




 See projects by country or transport mode

 

(Mailing address)
TEN-T Executive Agency
European Commission
W910
B-1049 Brussels
(Visiting address)
Chaussée de Wavre 910
B-1040 Brussels
Belgium