2011-ES-60002-P


ERTMS Deployment on the Madrid-Castilla la Mancha-Comunidad Valenciana-Murcia high speed line. Albacete-Alicante section


The action aims at the deployment of ERMTS on the Albacete-Alicante section of the Madrid-Castilla La Mancha-Comunidad Valenciana-Region de Murcia high speed line, which is part of Priority Project 19 (High speed rail interoperability on the Iberian peninsula).

 

Precisely, this action aims at equipping ETCS level 2 on the double-track of the railway line section from Albacete to Alicante. The ETCS Level 2 will comply with the baseline version 2.3.0d.

 

The Action will also cover the testing and certification processes. 

 

Budget:

 

Action promoter:

 

€4,438,000

 

Total project cost covered by this Decision:

 

€8,876,000

Percentage of EU support:

 

Works: 50%

EU contribution:

 

€4,438,000

 

Download the Info Sheet about this project:

.pdf (105.3 KB)

 

This project was also the subject of a press release issued by the Agency.

Click map to view enlarged version


Member States involved:

Spain

 

Implementation schedule:

Start date: January 2011

End date: December 2014

 

Beneficiary & Implementing body:

 Administrador de Infraestructuras Ferroviarias

 

Additional information:

 Coordinator’s Report of the Priority Project

 European Commission, DG MOVE




 See projects by country or transport mode

 

(Mailing address)
TEN-T Executive Agency
European Commission
W910
B-1049 Brussels
(Visiting address)
Chaussée de Wavre 910
B-1040 Brussels
Belgium