2010-EU-92240-S
Studies on improving the Freight Corridor Concept by using Telematic Applications for Freight, and methods, tools and procedures developed by RNE for rail corridors |
|
|
 |
|
The project supports the European Corridor Concept for by using the methods, tools and procedures already developed by the RailNetEurope organisation on defined RailNetEurope corridors. This project represents the continuation of the activities already started and carried out within the framework of the EU co-funded TEN-T project 2008-EU-90000-S.
The Action includes two activities:
- Activity I deals with evaluating and improving a harmonised timetabling process for international trains;
- Activity II tackles improving international cooperation between dispatching centres and Railway companies. This shall be done by implementing the international operational processes to ensure a good service and production quality in the international rail business.
This project has been completed.
|
Budget:
National budget:
€1,211,773
|
Total project cost covered by this Decision:
€2,423,546
|
Percentage of EU support:
Works: 50%
|
|
EU contribution:
€1,211,773
|
Download the Info Sheet about this project:
.pdf (230.5 KB)
This project was also the subject of a press release issued by the Agency. |
 |
 |
| Click map to view enlarged version |
Member States involved:
Austria
Implementation schedule:
Start date: September 2010
End date: June 2012
Beneficiary & Implementing body::
RailNetEurope
Additional information:
Coordinator’s Report of the Priority Project
European Commission, DG MOVE
|
|
|
|
|
|
 |
|
|
|
 |
(Mailing address) TEN-T Executive Agency European Commission W910 B-1049 Brussels |
 |