2011-IT-60001-P


Deployment of ERTMS trackside equipment on the Railway Corridor B Stockholm-Naples/Subpart Fortezza to Verona of the Italian Corridor B part (Brennero-Verona-Naples)


The proposed action consists of the deployment of ERTMS trackside equipment on the Verona-Fortezza route of the Italian part of ERTMS Corridor B. The deployment will be carried out on the concerned 200 km section of double-track railway line.

 

The Action aims at equipping the track-side of the railway line with the baseline version 2.3.0d, or 3 if available, with the ETCS Level 2 and Level 1 in some sections. 

 

The Action also covers the Action's management, the supervision of works, testing and authorisation processes.

 

Budget:

 

Action promoter:

 

€15,000,000

Total project cost covered by this Decision:
 

€30,000,000

Percentage of EU support:

 

Works: 50%

EU contribution:

 

€15,000,000

 

Download the Info Sheet about this project:

 .pdf (454.7 KB)

Click map to view enlarged version


Member States involved:

Italy

 

Implementation schedule:

Start date: January 2013

End date: December 2014

 

Beneficiary:

 Ministero delle Infrastrutture e dei Trasporti

 

Implementing body:

 Rete Ferroviaria Italiana

 

Additional information:

 Coordinator’s Report of the Priority Project

 European Commission, DG MOVE




 See projects by country or transport mode

 

(Mailing address)
TEN-T Executive Agency
European Commission
W910
B-1049 Brussels
(Visiting address)
Chaussée de Wavre 910
B-1040 Brussels
Belgium