2005-IT-90901-S
New AV/AC line Venezia-Trieste-(Lubiana) in Italian territory: sections project |
|
|
 |
|
The project concerns the preliminary design for high speed track of the railway section Venice-Trieste. In detail, are concerned the following subsections:
- from Venice Mestre to the underground Venice Airport station and Quarto d'Altino
- from Venice Santa Lucia to Venice Airport
- from the underground Venice Airport station to Bivio Dese
The project, closely correlated with project 2004-IT-90905-S concerning other sections on the same alignment, is part of the Priority Project 6 (Railway axis Lyon-Trieste-Divaca/Koper-Divaca-Ljubljana-Budapest-Ukranian border). As such, it contributes to shorten travel times for high speed passenger traffic.
This project has been completed.
|
Budget:
National budget:
€2,500,000
|
Total project cost covered by this Decision:
€4,500,000
|
Percentage of EU support:
Studies: 44.4%
|
|
EU contribution:
€2,000,000
|
Download the Info Sheet about this project:
.pdf (369.6 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
Italy
Implementation schedule:
Start date: December 2005
End date: December 2010
Beneficiary:
Republic of Italy
Implementing body:
Ferrovie dello Stato S.p.A.
Additional information:
Coordinator’s Report of the Priority Project