2006-EL(GR)-1014a-S
Suburban rail of Attica: Development studies |
|
|
 |
|
The Project concerns the performance of studies for three specific lines of the suburban railway ofAttica.
More specifically, the Project foresees studies for:
- the improvement of the alignment and the upgrading of the Inoi-Chalkida line, in order to achieve geometrical characteristics enabling speeds of up to 150 km/hour
- the Suburban Railway Line “Koropi Interchange-Lavrio” - Phase A for the extension of the Suburban Railway towards Lavrio
- the Suburban Railway Line Stavros-Rafina (Phase A)
This project has been completed.
|
Budget:
National budget:
€1,300,000
|
Total project cost covered by this Decision:
€2,600,000
|
Percentage of EU support:
Studies: 50%
|
|
EU contribution:
€1,300,000
|
Download the Info Sheet about this project:
.pdf (460 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
Greece
Implementation schedule:
Start date: January 2006
End date: June 2010
Beneficiary:
Hellenic Republic
Implementing body:
ERGOSE
Additional information:
European Commission, DG MOVE
|
|
|
|
|
|
 |
|
|
|
 |
(Mailing address) TEN-T Executive Agency European Commission W910 B-1049 Brussels |
 |
(Visiting address) Chaussée de Wavre 910 B-1040 Brussels Belgium |
 |
 |
 |
|
 |
|
 |
|