The project is part of Priority Project 17 from Paris via Strasbourg, Stuttgart, Munich to Vienna and Bratislava, Budapest.
It concerns the upgrade to high speed of the railway line Augsburg-Olching. By upgrading it to four tracks, high speed traffic can be separated from regional traffic.
It includes the following activities: planning, as well as upgrade of interlockings, switches, catenaries, railway security and telecommunication system, noise protection, railway crossings, land acquisition and ground works.
This project has been completed.
|
Budget:
National budget:
€45,440,000
|
Total project cost covered by this Decision:
€48,200,000
|
Percentage of EU support:
Works: 5.73%
|
|
EU contribution:
€2,760,000
|
Download the Info Sheet about this project:
.pdf (309.4 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
Germany
Implementation schedule:
Start date: January 2006
End date: December 2008
Beneficiary:
Federal Ministry of Transport, Construction and Urban Affairs (BMBVS)
Implementing body:
Deutsche Bahn AG
Additional information:
Coordinator’s Report of the Priority Project
European Commission, DG MOVE
|