Please note that this project has been cancelled
This project focuses on the preparatory study for the construction of the new rail connection Praha (Prague)-Beroun. This connection is part of the Czech Transit Railway Corridor on the branch Praha-Cheb/German border, as well as part of Priority Project 22, railway axis Athina-Sofia-Budapest-Wien-Praha-Nürnberg/Dresden.
The study includes a geotechnical survey and the subsequent project design documentation for the construction of the first Czech railway network built to high-speed specifications.
The project will contribute to improving safety and interoperability of high-speed tracks on Priority Project 22, and considerably reduce the travel time between Prague and Nürnberg.
|
Budget:
National budget:
€14,500,000
|
Total project cost covered by this Decision:
€29,000,000
|
Percentage of EU support:
Studies: 50%
|
|
EU contribution:
€14,500,000
|
Download the Info Sheet about this project:
.pdf (358.3 KB)
This project was also looked at during the Mid-Term Review of the 2007-2013 TEN-T Multi-Annual Work Programme. |
 |
 |
| Click map to view enlarged version |
Member States involved:
Czech Republic
Implementation schedule:
Start date: February 2008
End date: March 2011
Beneficiary:
Ministry of Transport
Implementing body:
Railway Infrastructure Administration (SZDC)
Additional information:
Coordinator’s Report of the Priority Project
European Commission, DG MOVE
|