2006-CZ-92109-S
Studies concerning the optimisation of the railway section between Mosty u Jablunkova at the Slovakian Border and Bystřice nad Olší |
|
|
 |
|
This project focuses on the final study for the modernisation of the railway section between Mosty u Jablunkova at the Slovakian Border and Bystøice nad Olší on the axis Ostrava-Žilina. This connection is part of Priority Project 23 Gdañsk-Warszawa-Brno/Bratislava-Vienna.
The study includes the project design documentation as well as all necessary geological and construction surveys to prepare the technical solution and to complete the geodetic and mapping data.
The project will contribute to improving safety and interoperability of high speed tracks on Priority Project 23.
This project has been completed.
|
Budget:
National budget:
€2,428,000
|
Total project cost covered by this Decision:
€4,828,000
|
Percentage of EU support:
Studies: 49.7%
|
|
EU contribution:
€2,400,000
|
Download the Info Sheet about this project:
.pdf (572.5 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
Czech Republic
Implementation schedule:
Start date: October 2006
End date: July 2007
Beneficiary:
Ministry of Transport
Implementing body:
Czech Railway Infrastructure Administration (SZDC)
Additional information:
European Commission, DG MOVE
|
|
|
|
|
|
 |
|
|
|
 |
(Mailing address) TEN-T Executive Agency European Commission W910 B-1049 Brussels |
 |
(Visiting address) Chaussée de Wavre 910 B-1040 Brussels Belgium |
 |
 |
 |
|
 |
|
 |
|