2009-AT-60153-P
ERTMS deployment on Corridor B (Stockholm-Naples) Austrian vehicles |
|
|
 |
|
The main objective of the Action is to achieve railway interoperability on the main section of ERTMS Corridor B by retrofitting certain number of freight locomotives with ETCS onboard units.
The implementation of the Action will contribute to the increase of the TEN-T railway network interoperability and in particular to the successful ERTMS deployment in the EU.
State of progress on 31 December 2011:
The technical specifications and contractual tasks have been completed. One prototype of "1216" type locomotive has been retrofitted and tests have started. The authorisation procedure has been defined. Retrofitting of "1116" type locomotives is ongoing.
|
Budget:
National budget:
€1,875,000
|
Total project cost covered by this Decision:
€3,750,000
|
Percentage of EU support:
Works: 50%
|
|
EU contribution:
€1,875,000
|
Download the Info Sheet about this project:
.pdf (386.6 KB)
|
 |
 |
| Click map to view enlarged version |
Member States involved:
Austria
Implementation schedule:
Start date: January 2009
End date: December 2013
Beneficiary:
Republic of Austria
Implementing body:
Österreichische Bundesbahn (OBB)
Additional information:
Coordinator’s Report of the Priority Project